ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The demolition in Rooms 211, 212, 233 and 236 is proceeding.

·         The contractor continued installing electrical conduit in the 1st Floor main corridor.

 

RESOURCE CENTER PERMANENT REPAIS & MITIGATION:

·         The contractor continued to run conduit for the new ATS room.

·         New copper water lines are being installed.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor drove 36 of the 50 wood piles needed for the new raised structure.

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor started installing the frames for the storefront system adjacent to the main corridor.

 

RESIDENCE HALL FIRE ALARM UPGRADE:

·         Contractor installed duct detectors for air handling unit 3 and removed inactive fire alarm wiring associated with the old fire alarm summary panel.

 

EXTERIOR/LANDSCAPING:

·         Facility Services planted shrubs in the planting beds on the Clinic Building side of the horseshoe.