TUESDAY, MARCH 30, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor lowered the drain for the water closets on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor completed building and setting the steel rebar cages for all 12 pile caps.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued to sand the existing door frames on the 1st Floor.
- Workers continued installing conduit on the 1st Floor for the emergency generator.
LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:
- The contractor installed sheetrock on the exterior wall.
EXTERIOR/LANDSCAPING:
- Facility Services planted trees and plants in the patio courtyard.
|