ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor continued installing electrical conduit in the main corridor on the 1st Floor.

·         The metal ductwork was removed from mechanical room 1A.

·         Workers cored four holes on the 2nd Floor needed for re-routed plumbing utilities.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor installed conduit for receptacles on the 1st Floor.

·         They removed 4 granite pavers in the front of the elevators and 4 granite pavers by the old security desk location.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor erected wooden forms for the four pile caps.

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor pulled wire from the electrical room to the lab.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor continued installing the storefront system.

 

RESIDENCE HALL FIRE ALARM REPLACEMENT:

·         The contractor completed transferring all of the new devices to the new fire alarm summary panel and activated the panel.

 

MEB MORGUE AUTOPSY ROOM HVAC UPGRADES:

·         The morgue passed the State Fire Marshal Inspection.

 

MEB MDL RENOVATIONS:

·         All four of the renovated Multi Disciplinary Labs passed the State Fire Marshal Inspection.

 

EXTERIOR/LANDSCAPING:

·         Facility Services continued grading the center island from the flagpole to Florida Avenue.