Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MAY 13, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued insulating and installing studs over the windows along Bolivar Street.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing underground conduit and piping underneath the grade beam.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor mounted an electrical panel box in the pump room on the 2nd Floor.

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

  • The contractor continued working on punch list items.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor ran additional conduit in the large conference room.

LANDSCAPING/EXTERIOR:

  • Facility Services completed the final grading and installed mulch on the Florida Avenue side and the parking lot side of the School of Dentistry Clinic Building.