MONDAY, MAY 17, 2010RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor installed four valves in the chilled water system in preparation for the installation of the elevated equipment. · Workers ran conduit from the new ATS room to the pump room on the 2nd Floor. · The concrete forms were removed from the new waterproof walls constructed for Elevators 3 and 4. CEB COVERED WALKWAY: · The contractor started setting up the abatement containment area. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor continued working on the remaining punch list items. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The AV contractor installed fiber cable for the speakers, microphone and projector in the large conference room, and for the dimmer panel in the AV room. |