MONDAY, MAY 24, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor re-routed the acid waste line around the auditorium column. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor saw cut the pavement for the utility trenches on the South Roman Street side. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor removed CMU blocks on the 1st Floor for Elevators 3 & 4. LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS: · The contractor continued to complete punch list items. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor completed wiring the light fixtures in the small conference room and the hallway. · Workers painted the large conference room black and patched the walls in the small conference room and the Directors office. CEB COVERED WALKWAY: · The contractor continued asbestos abatement of the active steam lines. · They completed demolition of the two abandoned pipe chases. LANDSCAPING/EXTERIOR: · Facility Services completed installing sprinkler stations and began grading the field side of the horseshoe drive at the School of Dentistry. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |