TUESDAY, MAY 25, 2010RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor compacted fill at the base of new building. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor began flood proofing the pits of Elevators 3 & 4. · Crews removed the flood line mark and cleaned the brick wall in the loading dock. · They began cleaning the granite on the SW corner of the loading dock. LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS: · The contractor continued to complete punch list items. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor continued to patch the walls in the small conference room and the Directors office. · Workers repaired the ceiling grid near the lounge and restrooms. CEB COVERED WALKWAY: · The contractor continued asbestos abatement of the active steam lines and continued demolition of the adjacent pipe chase. LANDSCAPING/EXTERIOR: · Facility Services completed the final grading on the field side of the horseshoe drive at the School of Dentistry. |