Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, MAY 4, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor continued roughing-in light fixtures in the restroom near the loading dock.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         Crews erected rebar cages and set forms for the new concrete walls in Elevators 3 & 4.

·         The contractor continued installing electrical conduit for emergency power.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor installed underground conduit in the electrical utility chase.

·         Crews constructed and erected rebar cages for the 12 columns that will support the new mechanical/electrical enclosure.

 

LIONS/LSU CLINC BLDG 7th FLOOR RENOVATIONS:

·         The renovated space passed the State Fire Marshal inspection.

·         The contractor installed cove base in the laboratory.

 

LANDSCAPING/EXTERIOR:

·         Facility Services continued placing and grading topsoil on the Florida Avenue side of the School of Dentistry Clinic Building.