ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor wired the restrooms lights and insulated the window wall near the MEB loading dock.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued running conduit and wire for the floor outlet in the main lobby on the 1st Floor.
- Workers continued installing electrical conduits for emergency power
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued erecting the concrete forms around the rebar cages for the 12 support columns.