FRIDAY, MAY 7, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor started laying out the structural steel supports and adjusted sprinkler heads on the 1st Floor.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor poured concrete for all 12 structural columns from grade to the 2nd Floor deck.

 

LANDSCAPING/EXTERIOR:

·         Facility Services completed placing and grading topsoil on the parking lot side of the School of Dentistry Clinic Building.