Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JUNE 23, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to run fire alarm cables to the 2nd Floor fire alarm panel.
  • Workers continue installing CMU walls on the 1st Floor.
  • They continue to form up the elevator wall.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed underground electrical conduit near the C Tower storage room on the Bolivar Street side.
  • Crews continue to build the concrete forms for the roof of the enclosure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to install the elevator pit parts for Elevators 3 and 4.
  • The concrete pad for the electrical transformer has been placed in the ATS room.
  • Workers continue to weld the chilled water bypass piping in the 2nd Floor pump room.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued installing geotextile fabric and spreading the limestone base material.

LIOHNS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor laid floor tile in the elevator lobby and glass tile on the reception area walls.