WEDNESDAY, JUNE 30, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued to run fire alarm cables to the 2nd Floor fire alarm panel.
- Crews started removing the mechanical room CMU wall on the 2nd Floor.
- They ran conduit and set the housing for the relocation of electrical panel D1A.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued removing the concrete forms from the bottom of the 2nd Floor.
- They completed installing underground waste line by the C Tower Roman Street side.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor installed 2 housings for electrical panels in the 2nd Floor switchgear room.
- Additional electrical conduits were installed in the switchgear room on the 2nd Floor.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor continued building the formwork for the corners and islands.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor completed installing the remaining carpet and tile on the floors.
- The AV contractor ran wires to the podium in the large conference room.