TUESDAY, JUNE 8, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued pulling the fire alarm cables to the 2nd Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued trenching on the South Roman side.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor began removing the temporary shaft wall for Elevators 3 and 4.
- Crews began running the electrical control wires to the ATS Room.
- A temporary construction wall was erected in the Bookstore.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor continued grading the site in preparation for the underground electrical installation. The excavated materials are being removed from the site.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor relocated the ductwork in the large conference room.
CEB COVERED WALKWAY:
- The contractor began surveying the site to determine the locations for the wood piles.