Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 13, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor removed outdated telephone and data wires from the telecom room on the 2nd Floor.
  • The 4th of 5 coats of fire proofing was applied to the structural steel beams.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The mechanical contractor continued installing the 1st of 4 elevated air handling unit platforms in the 1st Floor mechanical room.
  • The elevator contractor continued removing the pit parts from Elevators 1 and 2.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing the new electrical duct bank in the main driveway.
  • The contractor continued installing steel rebar in the concrete forms for the enclosure roof.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor continued grading the parking area in preparation for the asphalt paving.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued painting and installed the wood ceiling panels.