FRIDAY, JULY 16, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The general contractor completed applying the fire proof coating to the structural steel beams.
- The contractor completed re-installing granite panels surrounding the elevator lobby.
- The elevator sub-contractor continued installing pit parts in Elevators 1-3.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The electrical contractor pulled wires for the roof generator.
- The general contractor placed an AHU on the platform in the 1st floor mechanical room.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing the new electrical duct bank in the main driveway.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor completed the asphalt paving.
- They prepared for the electrical installation, demobilized the paving equipment and performed site clean-up.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The contractor installed cove base and doors.