Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JULY 20, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is continuing to construct CMU block walls on the 2nd Floor deck.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduits on the 8th Floor.
  • The general contractor continued to remove the 1st Floor CMU shaft wall for Elevators #1 and #2.
  • The contractor continued installing the raised platform for the second AHU on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor completed installing the new electrical duct bank in the main driveway.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor completed applying the markings to the parking lot.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The A/V contractor continued installing equipment in the large and small conference rooms.