FRIDAY, JULY 30, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued rewiring the electrical panels in the 1st Floor electrical room.
- Crews continued removing metal wall studs and floor tiles from Rooms 214, 218 and 219.
- They continued removing the heating hot water pumps from the 2nd Floor mechanical room.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor installed CMU shaft walls for Elevators 1 & 2 on the 1st Floor.
- They removed the access panels on the supply duct on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued the electrical rough-in for the 2nd level of the new elevated enclosure.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor built the forms and poured concrete for the curbing along all of the new sidewalks.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- Facility Services installed the sink in the break room.
- The contractor started installing the crash rails.