Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JULY 8, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to run conduit and work on the installation of electrical panel D1A.
  • Workers applied the first and second coats of the elevator shaft wall waterproofing.
  • The first of five coats of fire proofing were applied to the new structural steel beams.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued insulating the chilled water piping in the 2nd Floor pump room.
  • They began pulling wires in the new switchgear room on the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing underground electrical conduits and installed the 6 inch fire main underground in the main driveway and back-filled the area.
  • Steel reinforcement for the roof of the new addition was installed in the concrete forms.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor constructed sidewalks and installed protective bollards.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor continued installing wall paper, wood baseboard and the new millwork throughout the renovated space.
  • LSUHSC Computer Services installed the wireless access points.