Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, AUGUST 10, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor finished removing the granite panels from the 1st Floor elevator lobby.
  • Crews continue removing elevator pit parts.
  • The contractor continued removing the heat exchanger.
  • Door frames were installed in the stairwells along Bolivar Street.
  • They pulled wire for the lighting and elevator ATS.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor relocated fire alarm devices for the 2nd floor mechanical room.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 4 additional precast panels around the electrical and mechanical chase on the 1st Floor.
  • 16 of the 40 panels have been installed.

DENTAL SCHOOL PATIENT PARKING LOT:

  • Entergy connected power to the new electrical panel.
  • The contractor energized the panel and tested the parking lot lighting.

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor pulled access control wires within the wooden door frame.