Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, AUGUST 13, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor began removing the elevator shaft wall.
  • The heat exchanger has been removed.
  • Workers continued welding new heating hot water lines.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 4 additional precast panels on the 2nd Floor and roof level of the elevated mechanical/electrical enclosure.
  • 23 of the 40 panels are now in place.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to remove paint from the 1st Floor walls.
  • Crews continued to torque the bus duct in the switchgear room.
  • The granite thresholds for Elevators 1 and 2 were installed.

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued installing access control wire in the large conference room.