Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, AUGUST 17, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor started setting the forms for the elevator shaft wall.
  • Crews continued removing the heating hot water lines.
  • The ceiling in the main bridge area was removed.
  • Concrete was poured for the AHU on the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 5 additional precast panels on the 2nd Floor and roof level of the elevated enclosure.
  • 32 of the 40 panels have been installed.
  • Crews installed mounting bracket for light fixtures on the 2nd level.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to remove paint from the 1st Floor walls.
  • They continued to remove chilled water pipe from the 2nd Floor pump room.
  • Two sections of the existing fire alarm panel were removed.