Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, AUGUST 19, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor started installing the metal lath for the stucco walls in the Tiger Room.
  • Workers poured concrete for the elevator shaft wall.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed 2 additional precast panels on the 2nd Floor of the elevated structure,
  • 38 panels have now been installed and 2 remain.
  • Crews installed electrical conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began painting the 1st Floor walls.
  • They continued to remove chilled water pipe from the 2nd Floor pump room.
  • The contractor continued installing the pit parts for Elevators 1 & 2.