ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued rewiring the electrical panels in the 1st Floor electrical room.
  • Workers continued removing metal wall studs and removed floor tiles from Rooms 214 and 221.
  • A temporary wall was constructed in the 2nd Floor entryway.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor cleaned the ductwork on the 1st and 2nd Floors.
  • They started running new chilled water lines to the raised AHUs on the 1st Floor.
  • The contractor started removing existing paint in the stairwells.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued the plumbing rough-in for the 2nd level of the new structure.
  • Additional temporary fence was installed around the trailer holding the precast concrete panels.

DENTAL SCHOOL PATIENT PARKING LOT:

  • The contractor erected the uni-strut rack and poured the concrete foundation for the new electrical service equipment.
  • They installed the conductor wires for the parking lot lighting.
  • The new light poles were delivered.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The A/V contractor installed the podium in the large conference room.
  • The contractor continued installing the chair rails.