MONDAY, AUGUST 23, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The masonry contractor continued installing the metal lathe for the stucco walls in the Tiger Room.
- The mechanical contractor continued fabricating chilled water fittings for the 2nd Floor.
- The contractor installed foam board and rebar for the rear elevator shaft wall.
- Workers set the c-channel for 10 storefronts and set 1 of 19 storefronts on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing electrical conduits on the 2nd Floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The work has been completed on Elevators 1 & 2. They passed inspection and are back in normal operation.
- The contractor continued painting the 1st Floor walls.
LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:
- The AV contractor installed the podium and projector in the small conference room and one projector in the large conference room.
CEB COVERED WALKWAY:
- The contractor started fabricating the rebar for the walkway footings and setting up forms for the footings near the side entrance to the building.