FRIDAY, AUGUST 6, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor roughed-in for the pumps in the 2nd Floor mechanical room.
- Crews continued running copper lines for the pneumatic panel.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor set the new switch gear on the 2nd Floor.
- They continued cleaning ductwork on the 1st floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed 3 additional precast panels on the 1st Floor around the mechanical chase.
- 7 of 40 panels have been installed.
- Workers continued roughing in electrical conduits on the 2nd Floor.
DENTAL SCHOOL PATIENT PARKING LOT:
- The contractor repaired damaged asphalt throughout the parking lot.