TUESDAY, SEPTEMBER 14, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
- The contractor continued making fittings for the chilled water and heating hot water lines.
- Chilled water lines were installed near the stairwell.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor poured concrete for the equipment pads on the 2nd Floor.
- The electrical contractor continued installing conduits on the 2nd Floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor poured the concrete elevator shaft wall between Elevators 2 and 3.
- The electrical contractor continued to install lugs in the switchgear.
- The contractor continued to prime walls on the 1st floor.