Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, SEPTEMBER 16, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
  • The contractor continued making fittings for the chilled water and heating hot water lines.
  • They continued installing chilled water lines near the stairwell.
  • Additional elevator pit parts were installed in Elevators 4 & 5.
  • The contractor removed the exterior granite wall panels under the walkway.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor removed the wooden forms from the elevator shaft wall and installed CMU blocks to complete the shaft wall.
  • Workers continued to prime walls on the 1st Floor near the freight elevator.
  • Crews installed CMU blocks in the 1st Floor Womens restroom.