FRIDAY, SEPTEMBER 17, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
- The contractor continued making fittings and installed new heating hot water lines.
- Workers installed sump pumps for the freight elevator and Elevators 4 and 5.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued installing conduits on the 2nd Floor.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor began waterproofing the elevator shaft wall between Elevator 2 and 3.
- They began setting the interior door frames.