Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, SEPTEMBER 17, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
  • The contractor continued making fittings and installed new heating hot water lines.
  • Workers installed sump pumps for the freight elevator and Elevators 4 and 5.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began waterproofing the elevator shaft wall between Elevator 2 and 3.
  • They began setting the interior door frames.