Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, SEPTEMBER 20, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The masonry contractor continued installing metal lathe for the stucco walls in rooms along the Bolivar Street on the 1st Floor.
  • The contractor continued making fittings and installing new heating hot water lines.
  • Workers installed elevator pit parts for the freight elevator. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued installing conduits on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor set the door frames for Rooms 152, 144, and 116.
  • They tested the operation of Elevators 2 & 3.
  • Crews began installing the granite panels on the 1st Floor elevator lobby.

CEB COVERED WALKWAY:

  • The contractor set ten 8-ft steel columns and two 10-ft steel columns for the walkway section near the 1542 canopy.