FRIDAY, OCTOBER 1, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor has begun to apply stucco to the walls on the 1st Floor. Stucco was applied in Room 147.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor set the generator and a transformer in place on the 2nd Floor.
- They set transformers and disconnected boxes in place on the steel platform on the roof of the enclosure.
- Workers continued pressure washing the mechanical room on the 1st Floor, A-Tower.
|