Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, OCTOBER 19, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued applying the 3rd coat of stucco to the interior office space on the 1st Floor. 
  • Crews continued to install heating hot water lines on the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued placing the cap sheet layer of the roof on the new building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal lathe on the walls in Womens restroom.
  • They drilled 13 of 16 anchor bolt locations for the generator platform on the roof.
  • Workers replaced the 1st Floor windows and refinished the window frames on the Bolivar Street side of the building near Tulane Ave.