Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, OCTOBER 26, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued applying the 3rd coat of stucco to the Womens restroom and the 1st coat above the storefronts along Bolivar Street. 
  • Workers continued fabricating heating hot water lines for the 2nd Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractors began installing electrical conduits from the rooftop transformers through the roof. 
  • Crews began installing the generator exhaust pipe on the roof. 
  • The contractor began flashing the parapet wall. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor patched the concrete voids of the freight elevator shaft. 

CSRB EXHAUST UPGRADE:

  • The contractor installed a temporary wall in the 1st Floor corridor of the S. Prieur/Perdido quadrant in preparation for ceiling demolition.