WEDNESDAY, OCTOBER 6, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor applied the 2nd and 3rd coats of stucco to the stairwells along Bolivar Street.
- The continued removing chilled water lines and ran insulated heating hot water lines.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor mounted the first 2 of a total of 6 disconnect boxes on the roof platform.
- The exterior wall of the Maintenance Room (Room 11) on the 1st Floor, A Tower was primed.
|