Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, NOVEMBER 1, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed electrical fixtures and receptacles from Rooms 257 and 261. 
  • Workers continue to run heating hot water lines to the heating hot water pumps. 
  • They started demolition of the 2nd Floor AHU.
  • The contractor poured the raised concrete pads for the domestic water pumps. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continues to run the fuel line for the emergency generator.
  • Crews continue connecting the electrical conduit to the new switchgear. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor applied the 2nd coat of stucco at the freight elevator.
  • They applied the 3rd and final coat of waterproofing in the freight elevator pit.

CEB COVERED WALKWAY:

  • The contractor completed building the formwork for the grade beams at end of the walkway closest to the Medical School Building.
  • They continued building formwork for the main section of the walkway.