Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, NOVEMBER 11, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing studs for the 2nd Floor auditorium along the walkway side of the building.  
  • They demolished offices along Bolivar Street from the walkway to the Womens restroom. 
  • Additional copper piping for the AHU was installed in the 2nd Floor mechanical room.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor began pulling wires for the roof-mounted transformer. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor opened the wall of the penthouse for the generator platform supports.
  • Workers placed the diesel fuel line in Rooms 136, 138, and 155.

CEB COVERED WALKWAY:

  • Facility Services continued installing electrical conduit for the walkway lighting from the canopy closest to the Medical School Building to the District Energy Garage canopy. 
  • The contractor continued installing reinforcing steel at the canopy closest to the CEB in preparation for pouring concrete.

CSRB EXHAUST UPGRADE:

  • The contractor drilled two floor penetrations in the 6th Floor mechanical room for exhaust duct riser # 3.