Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, NOVEMBER 5, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running water lines to the heating hot water pumps.
  • They began pulling pneumatic tubing for the 2nd Floor AHUs.
  • Workers continued pouring the concrete equipment pads for the 2nd Floor AHUs.
  • The 2nd and 3rd coats of stucco were applied inside the 1st Floor offices above the door frames and around the columns.   

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractors continued connecting the electrical conduit to the new switchgear and the ATS.
  • A crew continued laying CMU block for the wall forming the domestic water pump room and the fire pump room. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor exposed the broken post tension cables in the ATS room on the 2nd Floor as they prepare to make repairs.

CEB COVERED WALKWAY:

  • The contractor completed installing the curved roof supports adjacent to the canopy at the District Energy Garage.
  • They installed the reinforcing steel for the grade beams at the canopy closest to the CEB. 

CSRB EXHAUST UPGRADE:

  • The contractor performed baseline air testing to determine and document the performance of the existing exhaust system.