Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, DECEMBER 15, 2010

ALLIED HEALTH PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for receptacles and light fixtures inside the auditorium.
  • They completed the wiring for the 1st Floor AHUs.      
  • The mechanical contractor continued fabricating fittings for the new domestic water pumps.
  • Workers ran heating hot water to VAVs and insulated the ductwork above the birthing labs on the 2nd Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued repairing the main roof.
  • CMU block wall is being laid for the storage room in C tower.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the emergency generator platform on the roof.
  • They applied roofing paper to the base of the emergency generator platform. 
  • The contractor continued to weld the fuel line for the emergency generator on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits in the basement to relocate existing electrical panels to the 1st Floor.
  • Workers removed the salt tank near the loading dock area.

CEB COVERED WALKWAY:

  • The contractor completed welding the steel canopy supports for the walkway roof.

CSRB EXHAUST UPGRADE:

  • The contractor ran spiral ductwork in the 1st Floor ceiling. 

DENTAL SCHOOL CAMPUS ROAD REPAIRS:

  • The contractor removed the formwork along both driveways and backfilled the perimeter.