Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, DECEMBER 17, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for receptacles and light fixtures inside the auditorium and set can lights in the auditorium ceiling.        

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor completed installation of the roof-mounted emergency generator.
  • The 1st Floor door to the freight elevator was repaired.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits in the basement to relocate existing electrical panels to the 1st Floor.

CSRB EXHAUST UPGRADE:

  • The contractor continued installing spiral ductwork in the 1st Floor ceiling. 

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor removed ceiling tiles in front of the gross anatomy and the pathology labs.