FRIDAY, DECEMBER 3, 2010
CEB COVERED WALKWAY:
- The contractor continued tack-welding the curved steel canopy supports for the walkway roof in place near the CEB.
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The electrical contractor continued running conduit for receptacles on the perimeter of the auditoriums.
- The demo contractor continued removing the remaining metal studs and electrical conduit from the offices along Gravier Street.
- The mechanical contractor continued installing ductwork in the 2nd Floor auditorium.
CSRB EXHAUST PROJECT:
- The contractor continued installing the temporary duct for phase 1 on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor continued placing tack-coating in trenches in the main driveway.
DENTAL CAMPUS ROAD REPAIRS:
- The contractor completed demolition of the driveway at Navy Blvd.