ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The electrical contractor continued running conduit for receptacles surrounding the auditoriums.  
  • The mechanical contractor continued installing and insulating ductwork in the 2nd Floor auditorium and along the Gravier Street on the 1st Floor.
  • They finished relocating the copper piping for the compressed airline.
  • Workers continue to work on the stucco punch list items on the 1st Floor.  

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the light fixtures in the new elevated structure.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor grouted the legs of the emergency generator platform on the roof.

CEB COVERED WALKWAY:

  • The contractor finished constructing the forms for the concrete steps leading to the back side of building. 
  • The contractor began welding the steel canopy supports for the walkway roof.

DENTAL SCHOOL CAMPUS ROAD REPAIRS:

  • The contractor installed concrete forms at the exit to Navy Blvd.
  • They fabricated and placed highway mesh and steel reinforcement along the two driveways.