ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to correct the stucco punch list.
  • They continued installing metal studs for the birthing labs on the 2nd Floor.
  • Sheetrock was installed on the exterior of the auditorium along Perdido Street. 
  • The contractor installed electrical conduit in the ceiling and in the wall in Room 138 for the AV in the Tiger Room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor ran temporary emergency power for the domestic water pump in preparation for the electrical shutdown scheduled for tomorrow.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the ceiling in the 1st Floor elevator lobby.
  • Workers continued correcting items on the stucco punch list.
  • The temporary generator was connected to the new emergency electrical panel

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running conduit in the basement to relocate electrical panels to the 1st Floor.
  • Crews continued removing brick pavers along the L & M lot.

CSRB EXHAUST UPGRADE:

  • The contractor relocated drain line on the 1st Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued to fabricate the 3 inch heating hot water riser for the penthouse. 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor removed 40 light fixtures from Rooms 6401 A-C on the 6th Floor of the Clinic Building.