Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JANUARY 21, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to correct items on the stucco punch list.
  • They continued running conduit from the emergency generator to the ATS on the 2nd Floor.   
  • Two of four floor penetrations in the 2nd Floor network closet were drilled.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor began painting the interior walls of the generator room on the 2nd level of the new addition.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the 1st Floor.
  • They began installing lightning projection for the rooftop generator.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits in the basement and on the 3rd Floor in preparation for relocating existing electrical panels.
  • Workers continued removing parts from the elevator pit for passenger elevators 7 & 8.

CSRB EXHAUST UPGRADE:

  • The contractor cut the floor penetration for the duct riser in Room 432A.
  • The exhaust duct riser was installed in the 7th Floor south mechanical room.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued to fabricate and install the chilled water lines for the AHU above Oral Pathology.

DENTAL SCHOOL STUDENT RECREATIONAL FIELDS:

  • The contractor is excavating for new storm drain lines.
  • Silt fencing was installed around the perimeter of the construction site.