ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • Workers continued to correct items on the stucco punch list.
  • They continued to run conduit from the emergency generator to the ATS on the 2nd Floor.
  • Conduit was run to relocate panel X1A (1st Floor emergency panel).   
  • The contractor applied self leveling compound to both 1st Floor restrooms. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor began painting the interior walls of the generator room on the 2nd level of the new addition building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued painting the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • Crews began installing the 10 inch pipe for the new heating hot water supply.
  • The pipes for the old heating hot water pump in the basement were removed.
  • The contractor continued removing parts from the elevator pit for passenger elevators 7 & 8.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued to fabricate and install the chilled water lines for the AHU above Oral Pathology.

DENTAL SCHOOL LIGHTING REPLACEMNT PROJECT:

  • The contractor replaced 20 light fixtures on the 6th Floor of the Clinic Building.