Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JANUARY 3, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running conduit for fixtures and receptacles on the 1st and 2nd floors.
  • Workers are constructing the ceiling fur-downs in the auditoriums.
  • The contractor primed and painted along the ceiling grid line. 
  • The architect approved the paint sample in room 138. 
  • The contractor continued to correct flaws in the stucco on the 1st Floor.
  • The steel beams for the generator platform were hung in the existing switchgear room on the 1st Floor. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the vibration isolator on the emergency generator.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits in the basement to relocate existing electrical panels to the 1st Floor.

CEB COVERED WALKWAY:

  • The contractor continued finishing the concrete for the two staircases.
  • They began installing the tapered supports for the canopy closest to the Clinical Education Building.

CSRB EXHAUST UPGRADE:

  • The contractor installed the rectangular exhaust duct that crosses the main supply duct on the 1st Floor.
  • Crews continued installing electrical conduit on 7th Floor near the freight elevator. 

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor installed the chilled water supply and return valves on the risers for the clinic area.
  • They installed the heating hot water supply and return valves on the risers for the clinic area.
  • Workers started the demolition of units 8B (Oral Pathology) and 8D (Gross Anatomy lab). 

DENTAL SCHOOL ABATEMENT PROJECT:

  • The contractor completed the 1st phase of abatement and passed all clearances. 

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • The contractor replaced 300 light fixtures in the 2nd and 4th Floor clinic areas, and in the 7th Floor pre-clinical laboratories. 

ALLIED HEALTH/NURSING BLDG NETWORK CLOSET:

  • The contractor removed the two doors and door frames leading into the lecture halls, removed the ceiling and started removing floor tile in the triangle room.