ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued running conduit for fixtures and receptacles on the 1st and 2nd Floors.
  • Workers continued to repair defects in the stucco on the walls of the 1st Floor.
  • Studs and door frames were installed for the birthing labs on the 2nd Floor. 
  • The contractor chipped out the concrete floor to allow for laying the AV conduit in Room 138. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor is installing electrical conduits in the basement for sump pumps.

CEB COVERED WALKWAY:

  • The contractor continued installing tapered supports for the canopy over the entry to the Clinic Education Building.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued with the ductwork (non-asbestos) demolition on units 8B (Oral Pathology) and 8D (Gross Anatomy lab).

DENTAL SCHOOL LIGHTING REPLACEMENT PROJECT:

  • 32 additional light fixtures were replaced on the 8th Floor of the Clinic Building (along the horseshoe side of the building).  

ALLIED HEALTH/NURSING BLDG 2ND FL NETWORK CLOSET:

  • The contractor painted the walls and installed plywood.