ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • Workers continued painting all four stairwells. 
  • The contractor continued installing the storefront on the elevated walkway and the structural steel for the new walkway window looking onto Gravier Street. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor completed pulling electrical feeders for the elevators. The building elevators are now energized through the new switchgear.  

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to prime the stainless steel doorframes on the 1st Floor.
  • Abandoned wiring was removed on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • They continued installing electrical conduits on the 3rd Floor for relocating panel 3LE. 

CSRB EXHAUST UPGRADES:

  • The contractor installed conduits on the 7th Floor near the mechanical room.

CEB COVERED WALKWAY:

  • The contractor continued to install the corrugated metal roof decking over the walkway.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued fabricating heating hot water and chilled water risers. 
  • They began pressure testing the chilled water lines for the AHU above Oral Pathology.
  • Supply ductwork for the AHU above Oral Pathology was installed. 
  • 10 light fixtures were replaced in the penthouse. 

DENTAL SCHOOL STUDENT ATHLETIC FIELDS:

  • The contractor has finished setting all 12 catch basins.
  • They continue trenching and connecting storm water piping.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed another 21 light fixtures on the 7th Floor of the Clinic Building.