Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, FEBRUARY 15, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the ceiling grid in the 1st Floor office area.   
  • They continued insulating the ductwork on the 2nd Floor. 
  • Workers started framing out the entryway fur down on the 2nd Floor. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor pulled 1 of the 2 feeders for the A/C on the ground floor to the new switchgear.
  • The first coat of epoxy paint was applied in the storage room and the laundry room in Tower A.
  • Workers continued to caulk the exterior concrete panels of the new elevated MEP building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor repaired the roof under the emergency generator.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water and chilled water piping in the basement.
  • They are rerouting the sewer line near the generator.
  • The contractor began installing the 4 inch electrical conduits in the basement.

CSRB EXHAUST UPGRADES:

  • The contractor primed the plaster ceiling on the 1st Floor.

CEB COVERED WALKWAY:

  • The contractor finished installing the corrugated metal roof decking on the main walkway sections.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued to fabricate the valve package for the VAV boxes. 
  • The VFDs for the air handling units above Oral Pathology and Gross Anatomy were hung. 
  • The VAV boxes and supply ductwork for the AHU above Gross Anatomy were installed. 

DENTAL SCHOOL STUDENT ATHLETIC FIELDS:

  • The continued clearing and grubbing the field.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor installed an additional 19 light fixtures on the 5th Floor of the Clinic Building.