Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, FEBRUARY 3, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor installed structural steel for the entryway storefront on the 2nd Floor. 
  • Workers continued laying the ceramic wall tiles in the 1st Floor restroom near the MEB loading dock.
  • They are pulling wire to the new raised emergency, life/safety generator.
  • Additional sheetrock was hung in the birthing labs on the 2nd Floor.
  • The contractor started roughing in the medical gasses for the birthing labs. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor removed the electrical transformer for the stoves in the B tower and removed the wiring for the stoves as they prepare to connect this riser to the new switchgear.   

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began finishing the interior walls in the bookstore that enclose the new switchgear.
  • They placed the cross beams for the mezzanine deck in the pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The concrete loading dock is being removed.
  • The contractor removed additional elevator pit parts from elevators # 4, 7, and 8.
  • They continuing to install conduit on the 2nd Floor. 

CSRB EXHAUST UPGRADE:

  • The contractor continued installing electrical conduit on the 7th Floor.

DENTAL SCHOOL AHU REPLACEMENT:

  • The contractor continued fabricating the heating hot water lines for the VAV boxes. 

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor replaced an additional 17 light fixtures. 

DENTAL SCHOOL STUDENT RECREATIONAL FIELDS:

  • The contractor backfilled the storm drain pipe trenches.
  • An additional catch basin was set in place. 4 of 12 catch basins have been installed.