Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MARCH 18, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the 2nd Floor elevator lobby.       
  • They ran power for the lectern in Room 138.     
  • The contractor welded structural steel in place below the walkway along the Gravier Street side of the building. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing heating hot water pipe in the 2nd Floor pump room and connecting the building side of the heating water system to the pumps. 

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing sewer pipes connecting to the new sewer man hole near the electrical duct bank in preparation for the tie-in tomorrow.
  • Workers formed and encased electrical conduit with concrete for the duct bank along the driveway and leading to the Entergy man hole.
  • The contractor continued welding and installing 8-inch chilled water pipes in the basement.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing re-heat lines to the VAV boxes in the corridor near the Oral Pathology labs. 
    • The contractor has completed 10 of 15 boxes.

  • The contractor continued running conduit from the control panels to the AHUs.
  • They pulled additional control wire for thermostats on the 8th Floor above the Oral Pathology unit. 
  • The contractor continued insulating supply ductwork in the penthouse for the unit above the Gross Anatomy.    

 DENTAL CAMPUS STUDENT ATHLETIC FIELDS:

  • The contractor continued final grading the softball outfield and the multi-purpose sports field.
  • A new catch basin was installed near the Administration Building.
  • They continued installing the softball backstop.

DENTAL SCHOOL LIGHTING REPLACMENT PROJECT:

  • The contractor replaced another 15 light fixtures on the 3rd Floor with new high-efficiency fixtures.