Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MARCH 25, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing three 4-inch standby power conduits.
  • Workers continued welding structural steel below the walkway along the Gravier Street side of the building. 
  • Thermostats were installed on the 1st Floor.
  • Glass partitions were installed in 1st Floor offices. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the sump pump for the B-Tower elevator.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor painted the lockers in the Mens and Womens locker rooms.
  • They continued installing heat exchanger piping on the building side.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor installed the last section of underground electrical conduit for the duct bank near the generator.
  • Crews continued welding and installing 8-inch chilled water pipes in the basement.

CEB COVERED WALKWAY:

  • The contractor finished installing the metal roof panels and flashing on the center section of the covered walkway.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor insulated the heating hot water lines near the Oral Pathology lab. 
  • The control wires for the AHU near Oral Pathology were installed. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING:

  • The contractor continued pressure washing the 1st bay on the south side of the Clinic Building and the cross-over section between the Administration and Clinic Buildings.

DENTAL SCHOOL LIGHTING REPLACEMENT:

  • The contractor replaced 17 light fixtures on the 4th Floor of the Clinic Bldg with new, high-efficiency fixtures.

DENTAL CAMPUS PARKING LOT LIGHTING:

  • Crews continued installing direct-buried electrical conduit between the new light pole bases.
  • Pole base # 24 was rejected last week and was demolished today.